CJSC Stroytransgaz has built tank farms in the Novorossiysk sea port and at the Kirishi Refinery, infrastructure for the Verkhnechonskoye deposit and other projects. Our current project portfolio includes the construction of the Kazachya compressor station, a basic facility of the Southern Corridor gas pipeline system where gas will be prepared for shipment to Europe via the South Stream pipeline.

 

Ongoing Projects

Execution
Schedule
Project
/ Investor
Customer Contract details











Completed Projects

Execution
Schedule
Project
/ Investor
Customer Contract details
2013-2015 Nevinnomissk Compressor Station / Gazprom Gazprom centrremont Full scope of reconstruction activities, including dismantle of the main and auxiliary equipment, as well as 6 turbo pumping unit installation (total capacity: 60 MW)
2012-2014 Alexandrovskaya Compressor Station / Gazprom Gazprom Transgaz Tomsk Full scope of reconstruction activities
More about the project

2011-2014 Mikun Compressor Station / Gazprom Gazprom centrremont Full scope of reconstruction activities
2014-2015 Facility for electrical equipment repair and maintenance base at Bovanenkovo oil-gas condensate field industrial base/ Gazprom Gazprom Dobycha Nadym Construction of facility for electrical equipment repair as well as a maintenance base. The two facilities are a part of the construction project for the development of the Cenomanian - Aptian deposits of the Bovanenkovo oil, gas and condensate field. The Bovanenkovo field is a priority development target in Yamal.
2015-2016 Mikun Compressor Station / Gazprom Gazprom centrremont Full scope of reconstruction activities on the second stage of station.
2012-2016 Kazachya Compressor Station (Southern Corridor gas pipeline project) / Gazprom Gazprom Invest General contract for construction (100 MW), including gas treatment facilities and all related infrastructure
More about the project
2012 Verkhnechonskoye Field / Verkhnechonskneftegaz Verkhnechonskneftegaz Construction of three well clusters (oil gather networks, oil pipelines and high pressure water conduit)
2008 Kirishi Refinery advanced oil processing center / Surgutneftegaz MSU-90 Reservoir assembly
2008 Petroleum products terminal / Novorossiysk Sea Port Yuzhtechmontazh Reservoirs assembly